Tool Gate · How it works
How the Allowance & Contingency Discipline Gate gate works
How the Allowance & Contingency Discipline Gate reads ten carried lines into one verdict: the roll-up is the share of allowance DOLLARS reading DEFINED rather than the share of lines, and a two-trigger definition gate forces PLACEHOLDER MONEY on any line with no written scope. The sample is 44% clean by count, 28% by value, and returns PLACEHOLDER MONEY.
How the gate works
This tool grades every allowance and contingency line on whether it names the scope it buys, and weighs the answer by dollars rather than by line. It reads 10 carried lines and rolls them into one verdict — the worst, never the average — and then a gate that can only make it worse.
The 10 carried lines
| Carried line | Verdict |
|---|---|
| AL-01 · Finish hardware · $42,000 | DEFINED100 · scope written, basis stated, owner named |
| AL-02 · Decorative lighting · $68,000 | DEFINED83 · no conversion date set |
| AL-03 · Signage package · $18,500 | DEFINED75 · exclusions not named |
| AL-04 · Landscape and irrigation · $95,000 | SOFT42 · scope thin, no basis for the number |
| AL-05 · Owner-selected tile · $31,000 | SOFT67 · not disclosed in the bid |
| AL-06 · Unforeseen site conditions · $140,000 | PLACEHOLDER25 · the largest line, and nothing says what it buys |
| AL-07 · Design development · $85,000fix first | PLACEHOLDER17 · no written scope at all |
| AL-08 · Millwork upgrade · $26,000 | DEFINED92 · owner named, conversion date set |
| AL-09 · Temporary weather protection · $12,000 | OUT OF SCOPEdeclared out of scope, and reported |
| AL-10 · Audio-visual rough-in · $54,000 | SOFT58 · scope written, no owner and no date |
The verdict bands
Two triggers. Any line with no written scope at all forces PLACEHOLDER MONEY, because nobody can convert a number when nothing says what it buys — that is not a thin allowance, it is the part of the bid that was not done. The second reads the whole book against the bid rather than any row: an allowance book at or above 15% of the bid total with under half its value defined. Without a bid total that second trigger reports NOT EVALUABLE rather than clear, because a gate that reads clear having read nothing is worse than no gate.
In the worked sample it reads PLACEHOLDER MONEY — Four of nine in-scope lines read DEFINED — 44% by count, which sounds survivable. By dollars it is 28%, because the two placeholders are the two largest lines on the page. The gate fires anyway: AL-07 carries $85,000 with no written scope at all, and no number of tidy small allowances beside it changes what happens at buyout. The one thing to fix first: AL-07 Design development · write the scope down — the gated line, ahead of the heavier ungated one.
Common questions
Can every carried line look survivable on the How the Allowance & Contingency Discipline gate works and the company still read PLACEHOLDER MONEY?
Yes. The roll-up takes the worst of 10 carried lines — never the average — then a worsen-only gate, the Definition gate gate, escalates when trouble clusters. In the worked sample it reads PLACEHOLDER MONEY because four of nine in-scope lines read DEFINED — 44% by count, which sounds survivable. By dollars it is 28%, because the two placeholders are the two largest lines on the page. The gate fires anyway: AL-07 carries $85,000 with no written scope at all, and no number of tidy small allowances beside it changes what happens at buyout.
What is a worsen-only gate?
A dispositive rule that can only lower a verdict, never raise it. One fatal flaw overrides an otherwise-set of survivable lines, because a single disqualifying gap shouldn't hide behind an average of the healthy ones. The tool also names the one thing to fix first — here, "AL-07 Design development · write the scope down — the gated line, ahead of the heavier ungated one".
Grades a register of carried lines you fill in, never a person. It reads no estimate, no bid, no drawing and no contract, never says what an allowance should be worth, does not judge whether the value you carried is enough, and takes no view on whether an allowance or exclusion clause would hold. Not legal advice.
Embed this diagram
Free to share and embed with attribution (CC BY 4.0) — keep the link to redhub.ai.
Interactive — renders the live diagram
<iframe src="https://redhub.ai/visuals/tool/allowance-contingency-discipline-gate.html" title="How the Allowance & Contingency Discipline Gate gate works — RedHub AI" width="760" height="2664" loading="lazy" style="border:0;width:100%;max-width:760px"></iframe>
<p style="font:14px/1.5 system-ui,sans-serif"><a href="https://redhub.ai/visuals/tool/allowance-contingency-discipline-gate">How the Allowance & Contingency Discipline Gate gate works</a> — by <a href="https://redhub.ai">RedHub AI</a>, the AI that tells you when to doubt it.</p>Image + link — a static picture for any blog
<a href="https://redhub.ai/visuals/tool/allowance-contingency-discipline-gate"><img src="https://redhub.ai/visuals/tool/allowance-contingency-discipline-gate-share.png" alt="Diagram of the Allowance & Contingency Discipline Gate: ten carried allowance and contingency lines each marked defined, soft or placeholder, one line flagged fix-first for having no written scope, a two-trigger definition gate weighed by dollars rather than by row, and a sample verdict reading PLACEHOLDER MONEY." width="760" loading="lazy" style="max-width:100%;height:auto;border-radius:16px"></a>
<p style="font:14px/1.5 system-ui,sans-serif"><a href="https://redhub.ai">RedHub AI</a> — the AI that tells you when to doubt it.</p>This is how Allowance & Contingency Discipline Gate works. More diagrams in the Visual Field Guide.